This £1.400K project lasted 26 week, involved the removal of Asbestos & other hazardous waste & the decommissioning of fuel tanks.

Multiple buildings were demolished along with basements which extended to 3m down below the slab level.

All suitable arisings were crushed & stockpiled for reuse on the 35 acre site.

Salvaged material from the work included over 4000 tonnes of steel which resulted in a significant price reduction for the client.

Client

Bovale Ltd

Location

Cheshire