Middlewich

This £1,368,000 project lasted 26 week and involved the removal of asbestos and the decommissioning of fuel tanks along with other hazardous waste, the demolishing of multiple buildings and basements down to 3m below slab level and the crushing and stockpiling of brick/concrete materials on a 35 acre site.
As we salvaged over 4000 tonnes of steel, the price reduction of the project cost for the client was significant.

Client

Bovale Ltd

Location

Cheshire