  • Former Rushdon and Diamonds Football Stadium

    This significant project was undertaken with HCD Ltd acting as principal contractor. Following the site set up, a complete soft strip was completed followed by the demolition of the stadium. Materials were crushed on site. Permanent hoarding was erected before a site clean up and demobilisation from the site.

  • Former Coleg Gwent Education Facility, Abergavenny

    Undertaking the works as a contractor, the twelve week project included asbestos removal, soft stripping, manual severs from two buildings to remain and remote demolition of several structures. Suitable materials were crushed to 6F2 and stockpiled onsite for future use.

  • Former Sinclair Horticulture Site – Lincoln

    HCD Ltd were appointed as the principal contractor to undertake the six week project. Works consisted of removing waste, the demolition of a large steel framed shed and small buildings, removal of Portakabins. A significant quantity of foundations were dug out before crushing 1086m³ of materials to 6F2 specification. The crushed materials were used to […]

  • Whitworth Mill – Peterborough

    The project consisted of soft stripping, asbestos removal and demolition of all buildings and silos with the exception of the original mill. To protect the mill building, manual severs were made to separate the adjoining structures. Running alongside the site, the River Nene had to be taken into account during the planning stage to ensure all […]

  • Coed Glas, Abergavenny

    Works were undertaken on the 1.93 hectare former council office site. Works consisted of tree and asbestos removal, soft stripping and demolishing all buildings down to slab level. Environmental concerns including bat, wildlife and protected trees were all given a high priority to eliminate any possible impact. Nearby neighbours were also considered with an open […]

  • Demoltion of Cascades Tewkesbury

    Cascades Tewkesbury

    A seven week project completed within the budget and timeframe. The high profile project involved asbestos removal, soft stripping and demolishing the entire leisure centre. All suitable materials were crushed and used to backfill the two former swimming pools. Finally, HCD  installed a fence around the site prior to handing the site back to the client. […]

  • Ludlow Demolition Project

    Ludlow

    The demolition of the flats was undertaken following soft stripping and asbestos removal. Materials were crushed to 6F2 specification and stockpiled on site for future use.

  • Tonbridge Demolition Project

    Tonbridge

    Two large office blocks were the focus of this project. Due to the location, the works were a high profile job with regular consultation undertaken with all stakeholders. Following asbestos removal, a complete soft strip was undertaken followed by remote demolitions of the offices. Concrete crushing and bulk earth removal was then carried out.

  • Epsom

    Project description Demolition of a large office block followed by concrete crushing and bulk excavation.

  • Presteigne Demolition Project

    Countrywide Farmers

    A 7 week, £134,000 project involved the removal of a large quantity of asbestos sheet cladding and hazardous materials from a redundant Feedmill attached to a ‘live’ warehouse. The Feedmill was demolished with a new gable-end being fitted to the live section of warehouse.

  • Former Alunna Tubes Demolition

    Former Alunna Tubes

    This 25 week, £569,500 project involved the removal of a large quantity of asbestos and other hazardous materials, the demolition of multiple superstructures (including removing in excess of 5000 tonnes of scrap metals) and the backfilling of vertical furnaces. Also included was the propping of a communications tower and the flushing out and sealing of […]

  • Former Lyte Ladders Demolition

    Former Lyte Ladders

    This £319,585 project on a 8.5 acre site over a 14 week period involved the removal of asbestos and the decommissioning of fuel tanks along with other hazardous waste, the demolishing of multiple buildings (which included removing 4800 tonnes of scraps metals) and basements down to 3m below slab level and the crushing and stockpiling […]

  • Droylsden Manchester Demolition

    Droylsden

    This £1,471,000 project over 50 week period involved the removal of asbestos and the decommissioning of fuel tanks, electrical sub-stations along with other hazardous waste, the demolishing of multiple buildings down to 1m below slab level, removing over 5400 tonnes of scrap metals and the crushing and stockpiling 24000 tonnes of brick/concrete materials on a 22 acre […]

  • Worcester Demolition

    Lowesmoor Trading Estate

    A three phase, £262,740 project on a 5 acre site that involved the careful demolishing and dismantlement of multiple buildings mainly constructed in pre and early Victorian era (circa 1791-1850). There was great archaeological interest in the site with the discovery of a Victorian railway line which fed the early Vinegar factory. This site was […]

  • Middlewich Demolition

    Middlewich

    This £1,368,000 project lasted 26 week and involved the removal of asbestos and the decommissioning of fuel tanks along with other hazardous waste, the demolishing of multiple buildings and basements down to 3m below slab level and the crushing and stockpiling of brick/concrete materials on a 35 acre site. As we salvaged over 4000 tonnes […]

  • Birmingham Broad Street Demolition Project

    Broad Street

    This £208,000 project involved the demolishing of multiple buildings in a busy urban environment on Broad Street, Birmingham which was completed three weeks prior to its planned 20 week schedule. Due to the location, this project involved the daily monitoring of noise and dust and the major challenges of dealing with substantial party wall issues.